Extended hours of work on Pineapple Road Station

There will be a closure of the railway line between 25th March to 3rd April to allow for 24-hour working on the new Pineapple Road station.

VolkerFitzpatrick will use this time to carry out work that can only be done while the railway line is closed. This includes things like as pouring concrete to create the platform foundations and starting to install platform units.

The closure of the line will also be an opportunity to remove significant volumes of excavated soil by train. This will minimise the number of muck-away lorries needed, reducing the impact of construction work on local roads.

Work has been carefully planned to reduce disruption as much as possible. Measures will be in place to monitor and reduce any noise. Lighting will be directed away from neighbouring areas.

To receive updates about West Midlands Rail Executive station projects, visit wmre.org.uk/wmrpnewsletter and sign up to the newsletter.

Leave a Reply

Your email address will not be published. Required fields are marked *

*